Anthropic's 2028 Power Mix: 87% Gas and 11% Coal, Per Better Data Center Project Analysis

Anthropic's contracted US data centers will be powered overwhelmingly by fossil fuels in the near term: the Better Data Center Project estimates that about 87% of the company's power will come from gas and 11% from coal in 2028. The finding matters because it quantifies, site by site, the emissions and health consequences of one AI lab's compute buildout — and because Anthropic has made no direct renewable energy commitments in the United States.

The analysis, published by the Better Data Center Project on November 16, 2026, is titled "How AI is powered: a breakdown of BYOP and grid power." It builds on the group's earlier report, "The AI Gas Rush: Risks and Implications of 'Bring Your Own Power,'" and uses a single company — Anthropic — as a case study of how the AI buildout is driving both on-site ("behind-the-meter") and grid-connected fossil infrastructure.

What "BYOP" means and why it matters

BYOP stands for "bring your own power": data centers securing their own dedicated primary generation rather than relying solely on utilities to procure power. The Better Data Center Project identified 177 GW of planned BYOP gas capacity in the United States — enough to power 65% of all US homes. For current proposals, the group estimates that less than 20% of energy generation will come from renewable sources by 2032.

BYOP is not the only new fossil source. The analysis states that another 200 GW of new fossil power plants is being built on the grid to meet growing demand, due in large part to data centers. The group cites the IEA and McKinsey as estimating that data centers are driving 50–75% of demand growth.

Finding 1: Anthropic has made no direct US renewable commitments

Anthropic has stated that it is "working to broaden our energy mix with geothermal, wind, solar, and emerging technologies," but as of November 2026 its only publicly disclosed renewable commitments, contracts, or investments are in Norway and Canada. In contrast, the analysis says Anthropic is directly procuring fossil power equipment: it recently "bought commitments for 1.7 gigawatts of heavy-duty [gas] generators for $3.4bn."

Finding 2: 87% gas, 11% coal in 2028

As of October 2026, Anthropic had contracted 15 GW of compute; of that, about 5.9–9.6 GW is contracted to specific data center sites. For scale, the analysis notes that 9.6 GW could power about 7 million homes or cover 18% of the peak power demand of California, described as the world's fourth-largest economy.

The Better Data Center Project attributes no grid renewables to Anthropic's power use in the short term. Its reasoning: without commitments to new renewable capacity, new load on the grid will be met by dispatchable, marginal fossil resources. The group cites WattTime and EPRI research on the emissions risks of data center buildout to support this marginal-generation approach.

Finding 3: 17–38 million MtCO2e per year in 2028

The analysis estimates that total CO2 emissions from Anthropic's power use at these sites could reach 17–38 million MtCO2e per year in 2028, when the capacity is expected to be online. The range reflects uncertainty in average power use, driven by factors such as cooling needs and average utilization. In the mid-case, the group estimates Anthropic will emit 32 million MtCO2e in 2028, and notes these totals could double by 2030 if analysts' expectations of 30 GW secured by 2030 hold.

The report places those figures in four contexts:

  • They could exceed the emissions of all of California's power generation (31.1 MMtCO2e in 2024, not including imports).
  • They could exceed Meta, Microsoft, and Google's combined Scope 2 emissions from 2025 — 5.9 million, 12 million, and 15 million MtCO2e respectively, on a location basis before renewable energy offsets.
  • They would represent a 16–36% increase over 2024 levels of the entire US data center sector (105 MMtCO2e).
  • They would increase the entire US power sector's emissions (1,485 MMtCO2e in 2025) by 1.1–2.5%.

The report adds a caveat: Anthropic's power-use emissions will likely be classified as a mix of Scope 2 and Scope 3 depending on whether it owns the GPUs, and Microsoft, Google, and Meta emissions are also expected to grow — so the comparison is not meant to suggest Anthropic will be the largest emitter among tech companies.

Finding 4: Anthropic's sites sit on coal- and gas-heavy grids

The analysis estimates the average carbon intensity of Anthropic's power at 1,033–1,076 lb CO2e/MWh — 35% higher than the US grid average of 767 lb CO2e/MWh. The group notes that using average (non-marginal) carbon intensity for each eGRID subregion would give 839 lb CO2/MWh, but argues marginal emissions are more representative of the near-term impact of added load.

Finding 5: 80% of on-site power uses simple cycle turbines and engines

About 25% (2.5 GW) of Anthropic's contracted power will come from on-site, behind-the-meter gas. Of that on-site capacity, 80% consists of inefficient simple cycle turbines and engines, which emit more pollution per unit of electricity than modern combined cycle plants.

Finding 6: $2–3 billion in annual health damages

Using the EPA's nationally averaged benefit-per-ton estimates, the analysis estimates that air pollution from Anthropic's on-site and grid power use could cause $2–3 billion in annual health damages, with total emissions of over 13,000 tons per year of nitrogen oxides (NOx) and 2,000 tons per year of fine particulate matter (PM2.5).

The report contrasts Anthropic's stated policy with its actual contracts. In October 2026, Anthropic outlined its "approach to responsible data center development," stating: "We follow the air permitting process everywhere we operate and require the same of the plants powering our data centers. Those plants must also use emissions control technology, including selective catalytic reduction [SCR]."

However, the analysis says Anthropic has used compute capacity at SpaceX's Colossus 2 facility since May 2026, which still receives most of its power from temporary, unpermitted turbines, the majority of which are not equipped with SCR. Anthropic will use as much as 600 MW of power from Colossus 2 by the end of 2026. Anthropic has also contracted 460 MW (and is in talks for up to 920 MW) of power from Nscale's Monarch Compute Campus in Mason, West Virginia — a facility the report says will be powered by inefficient reciprocating engines with significant formaldehyde and hazardous air pollutant emissions compared to conventional gas power plants.

Methodology: how the numbers were derived

The Better Data Center Project gathered data center commitments from Epoch AI's tracker, Anthropic's announcements and filings, partner announcements and filings (including Amazon and SpaceX), and reporting from The Information, Semafor, and others.

For projects with on-site gas (Monarch, Nexus, Colossus 2) or new grid gas — including indirectly contracted projects such as the Schahfer expansion for the AWS New Carlisle site and Entergy Mississippi's gas plants for AWS's Madison and Ridgeland facilities — the group used emissions factors from permits where available, or permit values from comparable facilities. For grid-connected facilities without associated new generation, it assumed marginal, dispatchable grid capacity and used the EPA's AVERT tool to model which plants would meet the new incremental load.

For power use, the group assumed power usage effectiveness (PUE) of 1.1–1.2 and power utilization of 60–80%. The mid-case assumes a PUE of 1.15, 70% utilization, and all 9.6 GW of identified compute capacity online in 2028.

How much capacity is Anthropic leasing from xAI?

Anthropic's initial May 6, 2026 announcement said the SpaceX agreement provided 300 MW of compute (220,000 GPUs). From SpaceX's revised June S-1A, the deal expanded to about $1.25 billion per month for 325,000 NVIDIA GPUs, with an implied IT power of about 490 MW. Based on Anthropic's October 2026 S-1, the deal has further expanded to $3.1 billion per month.

The analysis argues the increase in dollars per month is unlikely to produce a proportional 2.5x increase in compute capacity, since a June 2026 Google–SpaceX deal had a much higher cost (about $11.5 per GPU-hour versus about $5 per GPU-hour). As a rough estimate, the scaled deal likely corresponds to an additional ~200,000 GPUs, with total power of ~400 MW, with uncertainty of about ±25% for each figure.

What the Hacker News discussion added

The scale problem

Several commenters argued that the energy footprint of AI data centers is hard for most people to visualize. One commenter cited a data center proposed near Edmonton, Alberta:

"Utah State University physicist Robert Davies was hired by SLCN to conduct a preliminary technical assessment. He said if the Wonder Valley project goes ahead it would release the equivalent of 23 atomic bombs of energy every day, though he noted the comparison has its limits."

The same commenter added that the figure refers only to waste heat, and quoted Davies on consumption: "At full operation, it would consume energy at a continuous rate of 18 gigawatts or about 1.5 petajoules per day and emit about 30 million tonnes of carbon dioxide a year – more than four per cent of Canada's total emissions."

The grid and cost question

One commenter asked whether the US public can afford the added load, given a grid described as already stretched and rising electricity prices. Another framed the issue as one of externalities: "This is why we need regulation. Without rules, the cost of the externalities is passed on entirely to communities very far from leadership decision makers or shareholders."

Nuclear versus gas

A recurring question was why nuclear is not the default. One commenter answered with a comparison of carbon intensity: French nuclear (where Mistral is based) is around 5 gCO2/kWh, US gas plants around 300–350 gCO2/kWh, and Chinese coal plants around 800–900 gCO2/kWh — making a query to a French data center roughly 65x greener than one to a US data center. The same commenter attributed the US preference for gas to time-to-market: "It takes less than a year to setup a 1GW gas turbine. And close to 10y to setup a similar capacity in Nuclear."

Another commenter argued that natural gas is largely a byproduct of US shale oil production, sometimes trading negative in the Permian Basin, and that flaring it at the extraction site has a worse greenhouse effect than using it for power. The same commenter said nuclear "has been regulated into impossibility" and that solar would need massive land and battery capacity to serve a data center through winter nights.

Permitting and grid connection

One commenter argued that much behind-the-meter gas generation is caused by NEPA and other environmental review, citing a backlog of renewable projects that cannot get grid connection due to permit delays. Another proposed removing regulatory barriers so that generation and consumption can be grid-connected, letting wind and solar displace gas generators if the economics work out.

A commenter pushed back on Anthropic's permitting language: "We follow the air permitting process everywhere we operate. That doesn't mean much if they build in places with loose regulations."

Methodology critique

One commenter summarized the report's central modeling assumption and its limits:

"For grid-connected facilities without associated new generation capacity, we assume these sites will be powered by marginal, dispatchable grid capacity. Since all marginal capacity is basically gas and coal, the article assumes all data centers connected to the grid will be using >99% gas and coal. Also, the article focuses the short term impacts, so it doesn't account for how grids would adjust to the new demand over the long term."

Another commenter questioned why grid pollution per MW varies so much within a single state in the report's Figure 3, asking whether "grid" should not mean the draw is averaged among utility-scale generation plants.

Load-following and efficiency

One commenter asked whether any large-scale load-following data centers exist, arguing that data processing could shift to wherever energy is cheapest, which would suit renewables. Another predicted that "tokens per megawatt is about to go through the roof with things like disaggregated inference on the horizon," comparing future concern over AI power to worrying about how many trainloads of coal run everyone's WiFi router.

The political and reputational dimension

Several commenters framed the findings as a reputational risk for AI labs. One wrote that the labs "have failed entirely to predict this opposition and it's an existential risk to them." Another said Anthropic is "a legitimately bad actor here, particularly in leasing Colossus 1 given the local pollution it has caused in Memphis," and noted that Anthropic has made no US renewable commitments while Alphabet has made many.

A commenter in Flagstaff, Arizona described a community meeting on data centers organized around the site noazai.org, and said a speaker attributed 90% of the power and environmental problems to power generation rather than the data centers themselves. The commenter's preference was to slow data center development for 5 to 10 years, fix infrastructure, then build out more robustly.

Others argued for stronger mandates. One proposed requiring new data centers to procure 110% renewable energy capacity. Another called for Congress to require companies to build new batteries and renewables within a reasonable time frame instead of receiving tax breaks. A third suggested data centers could afford carbon sink systems and questioned why they are not implementing them.

The counterpoints

Not every commenter treated the fossil mix as a failure. One argued that gas is "fair in terms of pollution" and that maintaining the ability to turn off a power source matters if AGI is near. Another pointed to economics: model providers directly feel the cost of power generation, revenue does not come close to buildout costs, and the incentive to lower costs is massive — with large inference-cost gains already achieved.

A commenter suggested siting data centers in the Sahara with solar, storage, and closed-loop water cooling, arguing that a small amount of latency would have limited impact. Another noted that Mistral is building in France, which has a 95% low-carbon energy mix, and said that for regular chat questions there is no meaningful difference between top-tier models — implying that switching providers is a viable lever for users who care about emissions.

The bottom line

The Better Data Center Project's analysis concludes that Anthropic's contracted US data centers will be overwhelmingly fossil-powered in 2028 — about 87% gas and 11% coal — with 17–38 million MtCO2e in annual power-related emissions, a carbon intensity 35% above the US grid average, and $2–3 billion in estimated annual health damages from NOx and PM2.5. The report's own methodology notes that these are short-term marginal-emissions estimates, and commenters on Hacker News debated both the modeling assumptions and the policy responses — from renewable procurement mandates and grid-connection reform to nuclear buildout and simply choosing lower-carbon providers.